DESIGN
CONSTRUCTION
PLANNING
POST-CONSTRUCTION
instructor shall train the Government employees designated by the Contracting
Officer in the care, adjustment, maintenance and operation of the new facility
equipment and systems. Each instructor shall be thoroughly familiar with all
parts of the installation. The instructor shall be trained in operating theory as well
as practical operation and maintenance work.
Turnover Commissioning Record
Review Submittals for
It is critical to understand that commissioning documentation is developed
Performance Parameters
throughout the project & turned over before substantial completion. Commissioning
Develop & Utilize Construction
Checklists
documentation turned over at this stage of the project is a result of a well thought
Oversee & Document Functional
out documentation plan and collection of information throughout all of the project
Performance Testing
phases. The following matrix outlines necessary documentation of the commis-
Hold Cx Team Meetings and
sioning process by project phase in order to complete the Commissioning Record.
Report Progress
Conduct Owner Training
Commissioning Record Document
Turnover Commissioning
Developed/Provided By
Document
Phase Started
Record
Commissioning Plan
Planning
GSA PM
Commissioning Plan Appendices
System Performance
Documented & Accepted
A. Owner's Project Requirements
Planning
GSA PM
B. Basis of Design
Design
A/E
C. Commissioning Specifications
Design
A/E/CxA
GSA PM Lead
D. Design Review
Design
CxA
CxTeam Support
CxA Lead
E. Submittal Review
Design
CxA
CxTeam Support
F. Test Procedures
Design
CxA
Customer Agency
Lead
G. Issues Log
Construction
CxA
Final Phase
Step
H. Construction Checklists
Construction
CxA/Construction Contractor
I. CxA Site Visit & Cx Team Mtg. Minutes
Construction
CxA
building commissioning
44
process