The Commissioning Progress Reports shall be distributed to the entire
Commissioning Team.
Conduct Owner Training
An important step in the commissioning process is ensuring that GSA Operating
Personnel are properly trained in the required care, adjustment, maintenance
and operations of the new facility equipment and systems. It is critical that
Review Submittals for
operations and maintenance personnel have the knowledge and skills required
Performance Parameters
to operate the facility to meet the Owner's Project Requirements. Training shall
Develop & Utilize Construction
Checklists
specifically address:
Oversee & Document Functional
Step-by-step procedures required for normal day-to-day operation of the facility
Performance Testing
Hold Cx Team Meetings and
Adjustment instructions including information for maintaining operational pa-
Report Progress
rameters
Conduct Owner Training
Troubleshooting procedures including instructions for diagnosing operating
problems
Turnover Commissioning
Record
Maintenance and inspection procedures
Repair procedures including disassembly, component removal, replacement and
reassembly
System Performance
Upkeep of maintenance documentation and logs
Documented & Accepted
Emergency instructions for operating the facility during various nonstandard
conditions and/or emergencies
Key warranty requirements
GSA PM Lead
CxTeam Support
Commissioning Agent Role in Training
CxA Lead
CxTeam Support
Because of the Commissioning Agent's in-depth knowledge of the design intent
Customer Agency
and building systems, it is important to have the CxA intimately involved in the
Lead
training. The CxA is responsible for facilitating the entire owner training process.
Final Phase
Step
This process begins in the Design Stage by assuring that appropriate levels of
training are planned and included in the specifications. The CxA maintains a
system-based as opposed to component-based focus in the training to ensure
building commissioning
42
process