DESIGN
CONSTRUCTION
PLANNING
POST-CONSTRUCTION
Complete Final Commissioning Report
During Post-Construction, the Commissioning Agent is responsible for delivering
a Final Commissioning Report. This document is additive to those items detailed
in the "Turnover Commissioning Record" section. The Final Commissioning
Report shall include at a minimum:
Perform Deferred & Seasonal
A statement that systems have been completed in accordance with the contract
Testing
documents and that the systems are performing in accordance with the final
Owner's Project Requirements document
Reinspect/Review Performance
before End of Warranty Period
Identification and discussion of any substitutions, compromises or variances be-
Complete Final
tween the final design intent, contract documents and as-built conditions
Commissioning Report
Description of components and systems that exceed Owner's Project Requirements
Final Satisfaction Review
and those which do not meet the requirements and why
with Customer Agency
Summary of all issues resolved and unresolved and any recommendations for reso-
lution
Post-Construction activities and results including deferred & seasonal testing re-
Recommission Facility Every
3-5 Years
sults, test data reports and additional training documentation
Lessons learned for future commissioning project efforts
Recommendations for changes to GSA standard test protocols and/or facility de-
sign standards (i.e. GSA P-100, etc.)
System Performance
Sustained
The Final Commissioning Report will serve as a critical reference and benchmark
document for future recommissioning of the facility.
In addition, the CxA is responsible at this stage to assure the A/E's update to the
GSA PM Lead
CxTeam Support
CAD As-Built drawings is completed.
CxA Lead
CxTeam Support
Final Satisfaction Review with Customer Agency
Customer Agency
Lead
As one of the benefits of commissioning is to increase occupant and user satis-
Final Phase
faction, it is important that the GSA PM lead a final satisfaction review with the
Step
Customer Agency. This review shall occur at one year after occupancy (according
to GSA's Facility Performance Evaluation Process). Minimum attendees shall
building commissioning
51
process