sample scope f or commissioning
ser vices
Scope and Procurement
The General Services Administration (GSA) requests written proposals to secure
Approach
Commissioning Agent (CxA) services for the <PROJECT NAME> facility in
If Commissioning services
<PROJECT LOCATION>. GSA is committed to commissioning this facility to
are to be incorporated into
the contract of a CM, which
ensure that all systems are well designed, complete and functioning properly
is procured using source
upon occupancy, are economical to operate and maintain, and that GSA staff has
selection procedures, then
the following material offers
adequate system documentation and training.
sample language that can
be incorporated into the
scope for the CM. Scope
Background
of Work material can be
considered adapted to suite
GSA is seeking the services of a qualified commissioning provider/firm for
either Brooks Act or IDIQ
work order procurements.
this new construction project. The project currently is a <INSERT PROJECT
DESCRIPTION INCLUDING SIZE, FACILITYTYPE, PROJECT BUDGET, GENERAL
PROGRAM, DELIVERY METHOD AND MILESTONE SCHEDULE OVERVIEW>.
Objectives
The objective of commissioning is to provide documented confirmation that a
facility fulfills the functional and performance requirements of GSA, occupants
and operators. To reach this goal, it is necessary for the commissioning process
to establish and document Owner's Project Requirements, which are criteria
for system function, performance, and maintainability (design intent); and to
also verify and document compliance with these criteria throughout design,
construction, start-up, and the initial period of operation. In addition, complete
operation and maintenance (O&M) manuals, as well as training on system
operation, shall be provided to the building operators to ensure the building
continues to operate as intended.
The CxA shall be involved throughout the project from design development through
the warranty phase. The primary role of the CxA during the overall Design Stage
is to review the design to ensure it meets GSA objectives and develop detailed
commissioning specifications. During construction, the CxA coordinates the
execution of a testing plan, which includes observing and documenting all
systems' performance to ensure that the systems are functioning in accordance