Recommissioning shall generally include:
Establishing that original basis of design and operation is still appropriate for use,
occupancy, tenant agencies and GSA goals, and modify the operations/controls
sequencing as appropriate for optimum operations
Reviewing and benchmarking key systems operations/performance against the
Basis of Design
Performing energy analysis
Recommending repairs/modifications to optimize building performance
It is important to recognize that at 3-5 years after occupancy, the GSA PM will
likely not still be involved with a particular project. Therefore, the Customer
Agency will take the lead on facility recommissioning. Recommissioning shall
include Commissioning Agent services. While there are obvious benefits of famil-
iarity, the Customer Agency may or may not bring back the project Commissioning
Agent. Recommissioning is not part of the original CxA's contract, and therefore
the Customer Agency must procure these services through a RFQ/RFP process
at the time of recommissioning.