include the Commissioning Team and other selected Customer Agency represen-
tatives.
The purpose of this review is to obtain honest, objective and constructive
feedback on what worked well throughout the commissioning process and what
the Commissioning Team could have done better. The group shall be focused
on identifying root causes and proposing corrective action for future projects.
Perform Deferred & Seasonal
Specific discussion topics may include:
Testing
Reinspect/Review Performance
Owner's Project Requirements
before End of Warranty Period
Systems selected for commissioning
Complete Final Commissioning
Report
Coordination issues
Final Satisfaction Review with
Commissioning budget and costs
Customer Agency
Commissioning schedule relative to project schedule
Occupant comments/complaints
Recommission Facility Every
3-5 Years
Documentation issues
Lessons learned
The GSA PM takes the lead on documenting this session in a formal lessons
learned report. This information will be an important input to future projects.
System Performance
Sustained
Recommission Facility Every 3-5 Years
At this stage of operation a considerable investment has been put into assuring
GSA PM Lead
the facility operates as intended. Understanding that systems tend to shift
CxTeam Support
from their as-installed conditions over time due to normal wear, user requests
CxA Lead
CxTeam Support
and facility modifications, it is strongly recommended that Customer Agencies
Customer Agency
consider recommissioning facilities every 3-5 years. A facility recommissioning
Lead
program serves to assure operational efficiency and continued user satisfaction.
Final Phase
Maintaining good O&M and occupant complaint records is key to continued
Step
recommissioning efforts.