DESIGN
CONSTRUCTION
PLANNING
POST-CONSTRUCTION
It is recommended that the CxA is contracted according to a two phase fee
negotiation process. The first phase includes Design Stage responsibilities and
the second phase includes Construction and Post-Construction activities. This
two phase process allows for the negotiation of the initial fee to be based on known
general factors, and negotiation of the Construction and Post-Construction Stage
fee based upon a substantially completed design and the actual type and number
of equipment, systems and assemblies to be inspected, started and tested.
Within the Design Stage proposal, the CxA shall be asked to provide budgetary
A/E & CM Scope of Services
numbers for the Construction and Post-Construction Stages.
Retain Commissioning Agent
Services
Review Owner's Project Requirements & Basis of Design
Review Owner's Project
Requirements & Basis of
As described in previous sections, the Owner's Project Requirements are
Design
developed as part of GSA's project planning processes and establish baseline
Concept, DD and CD Design
Reviews
criteria for facility function, performance and maintainability. The Basis of
Update/Refine Commissioning
Design (BOD) is developed by the A/E early in the Design Stage based on Owner's
Plan
Project Requirements. It is the primary document that translates GSA's and the
Develop Commissioning
Customer Agency's needs into building components such as HVAC systems,
Specifications
building envelope, security systems, building automation system, etc. The BOD
describes the technical approach planned for the project as well as the design
Contact Documents Aligned
with Owner's Project
parameters to be used. The BOD is typically developed by the A/E and done in
Requirements
technical terms, whereas the Owner's Project Requirements are developed by
GSA in concert with the Customer Agency and expressed in layman's terms.
GSA PM Lead
When the Commissioning Agent is brought on board early in the design
CxTeam Support
development phase, one of their first tasks is to review the Owner's Project
CxA Lead
Requirements and the Basis of Design (BOD). The purpose of these reviews is
CxTeam Support
to assure that the Customer Agency's needs are met as described in the Owner's
Customer Agency
Lead
Project Requirements, and carried through in the Basis of Design Document.
Final Phase
The CxA's review ensures clarity and completeness with an eye toward commis-
Step
sioning process activities (benchmarks, standards, performance targets, etc.).
The CxA may recommend changes to improve energy efficiency, operation &
building commissioning
27
process