DESIGN
CONSTRUCTION
PLANNING
POST-CONSTRUCTION
O&M Documentation
Verify adequate building O&M documentation requirements.
Owner's Project
Verify that contract documents are in keeping with and will meet the
Requirements
Owner's Project Requirements.
Review the structural concepts/design for enhancements (i.e. blast &
Structural
progressive collapse).
Review to ensure that the building materials, landscaping, water
& waste management create less of an impact on the environment,
Sustainability
contribute to creating a healthful & productive workspace, & are in ac-
cordance with Owner's Project Requirements. See also P-100 LEED
requirements.
Training
Verify adequate operator training requirements.
Issues Log
All comments and issues identified must be tracked in a formal Issues Log. The
Issues Log must be sufficiently detailed so as to provide clarity and a point of
future reference for the comments. The Issues log shall contain at a minimum:
Description of Issue
Cause
Recommendation
Cost & Schedule Implications (on design, construction & facility operations)
Priority
Actions Taken
Final Resolution
The Issues Log serves as a vehicle to track, critically review and resolve all
commissioning related issues. The Log is maintained by the CxA and becomes
Design Review Meetings
The Cx Team shall have a minimum of 3 Design Review Meetings (Kick-off,
building commissioning
30
process