DESIGN
CONSTRUCTION
PLANNING
POST-CONSTRUCTION
Concept/DD and CD). Additional meetings may be required to resolve outstanding
issues. The CxA is responsible to lead design review meetings and work collabora-
tively with the CommissioningTeam toward presentation, discussion and resolution
of design review comments. Upon resolution of the CxA's comments, the A/E is
responsible to incorporate all approved changes into the design documents.
Update /Refine Commissioning Plan
Incorporate Commissioning into
Now that the Commissioning Agent is on board and has performed Design Stage
A/E & CM Scope of Services
reviews, the team realigns & updates the Commissioning Plan in preparation
Retain Commissioning Agent
Services
for the Construction Stage. The Commissioning Team shall formally accept
Review Owner's Project Re-
the updated Commissioning Plan before moving into construction. Further, all
quirements & Basis of Design
outstanding comments and issues relative to the CxA's review of the design shall
Concept, DD and CD Design
be resolved, and accepted changes shall be incorporated into the contract and
Reviews
construction bid documents.
Update/Refine
Commissioning Plan
Commissioning team directory
Develop Commissioning
Commissioning process activities
Specifications
Roles & responsibilities
Communication structures
Contact Documents Aligned
with Owner's Project
Commissioned systems & equipment
Requirements
Commissioning process schedule
Appendices (Owner's Project Requirements, BOD, Design Review, Issues Log)
GSA PM Lead
The Commissioning Team shall formally accept the updated Commissioning Plan
CxTeam Support
before moving into construction. Further, all outstanding comments and issues
CxA Lead
relative to the CxA's review of the design shall be resolved, and accepted changes
CxTeam Support
Customer Agency
shall be incorporated into the contract and construction bid documents.
Lead
Final Phase
Develop Commissioning Specifications
Step
The commissioning tasks for the contractors will be identified in the commis-
sioning specifications and will include:
building commissioning
31
process