General commissioning requirements common to all systems and assemblies
Fire Protection Engineering & Life
Safety
Detailed description of the responsibilities of all parties
To ensure that no aspect of a
building's design or operation
Details of the commissioning process (i.e. schedule and sequence of activities)
presents an unacceptable risk, a
Reporting & documentation requirements & formats
fire protection engineering and life
safety assessment is required in
Alerts to coordination issues
the Pre-Planning Phase (see GSA's
Project Planning Guide).
The
Deficiency resolution
CxA's role in commissioning of fire
protection & life safety systems
Commissioning meetings
is to assist the GSA regional fire
protection engineer.
Submittals
O&M Manuals
Construction checklists
Functional testing process and specific functional test requirements including test-
ing conditions and acceptance criteria
As-built drawings
Training
Specifications must clearly indicate who is witnessing and documenting start-
up of each commissioned system. Specifications must also clearly indicate
who is writing, directing, conducting and documenting functional tests. The
Commissioning Agent and the A/E must work together to ensure that commis-
sioning requirements are fully integrated and coordinated in the project
specifications.
Written Test Procedures
Written functional test procedures define the means and methods to carry out
system/intersystem tests during the construction phase. To the extent possible
these test procedures shall be defined by the Commissioning Team in the Design
Stage and written into contractors' scopes of work. Test procedures will neces-
sarily be refined early in the construction phase based on the submittal process.
Tests procedures provide the following: