A/E & CM Commissioning Scope Items
Design Professional
Construction Manager
1. Participate & aid in the documentation of the
1. If appropriate, lead the RFQ process for
Owner's Project Requirements.
commissioning services and award a contract
to a Commissioning Agent directly under the
2. Document revisions to Owner's Project
Construction Manager.
Requirements and obtain GSA Approval.
2. Include commissioning process activities and
3. Document the Basis of Design.
requirements into all General Contractor Bid
Packages.
4. Integrate Cx process requirements & activities
provided by the CxA into the contract docu-
ments.
5. Attend Commissioning Team meetings
overall project schedule
(3 Design Review Meetings and monthly
Construction Stage Cx Team meetings).
4. Provide personnel with the means and author-
ity to coordinate implementation of the com-
6. Specify & verify that the operation & mainte-
missioning process as detailed in the contract
nance of the systems & assemblies have been
documents.
adequately detailed in the construction docu-
ments.
5. Attend Commissioning Team meetings
(3 Design Review Meetings and monthly
7. Review & incorporate as appropriate the CxA's
Construction Stage Cx Team meetings).
comments into the contract documents.
6. Coordinate with the Commissioning Agent in
8. Participate in the operations and maintenance
development of a Commissioning Plan.
personnel training as specified in the training
program.
7. Perform quality control functions, particularly
in the areas of design reviews for constructability
9. Review test procedures submitted by the con-
and inspection.
tractor.
8. Participate in and assist with the functional
10. Review & comment on the CxA's progress
testing of all commissioned systems and assem-
reports and issue logs.
blies.
11. Witness the functional testing of all commis-
9. Provide technical expertise such as testing,
sioned systems and assemblies.
cost estimating and resolving disputes.
12. Review and accept record documents as
10. Coordinate & document Owner/Operator train-
required by the contract documents.
ing.
13. Review and comment
on
the
final
11. Issue a statement that certifies all work has
Commissioning Record.
been completed and the facility is operational, in
14. Recommend final acceptance of the systems
accordance with the contract documents.
to GSA.
12. Coordinate General Contractor remedies for
15. Verify systems are installed as specified.
deficiencies identified by the Commissioning
Agent during their verification of the installation
or tests.
13. Review and comment
on
the
final
Commissioning Record.
building commissioning
24
process