and P.E. license is desired; however, other technical training, past commissioning,
and field experience will be considered.
Membership with the Building Commissioning Association is desired.
Membership with the US Green Building Council is desired.
Leadership in Energy and Environmental Design (LEED) Accredited Professional
is desired.
The required expertise for this project will be based on the skill and experience
set of the full team making the proposal. A member of the prime firm will be
the designated Commissioning Agent who is the member of the team that will
coordinate the commissioning activities from the technical perspective. This
party may not necessarily be the team's overall project or contract manager.
The Commissioning Agent must have significant in-building commissioning
experience, including technical and management expertise on projects of similar
scope. If the Commissioning Agent or prime firm does not have sufficient skills to
commission a specific system, the prime firm shall subcontract with a qualified
party to do so. Subcontractor qualifications shall be included and clearly desig-
nated in the response to this scope of work.
Proposal
The Proposal need not be voluminous, but shall provide sufficient information to
allow GSA to evaluate the Consultant's approach, experience, staff and availability.
The proposer shall:
1.
Limit their proposal to 15 single-sided pages, including graphics. A letter of intro-
duction, section dividers, detailed resumes and the sample work products of item
five below are not included in this limit.
2.
Have the proposal signed by an officer of the proposing firm with the authority to
commit the firm.
Fill out the attached Commissioning Firm Experience form and the Commissioning
3.
Task Listing form (Exhibits 2
and 3)
for each firm on
the team. List no
more than
four projects in Exhibit 3.
4.
Provide an organization chart for managing and executing this contract.
67
67
appendices