8.3 Commissioning
The design team's security consultant/engineer shall
Construction Manager, Project Manager, and (if contract-
project's programmed performance goals. As appropriate,
coordinate with other disciplines to fully enable required
testing and certifications. Incorporate into construction
specifications those testing and certification requirements
that involve construction contractors. Examples of
possible programmed performance goals, include:
HVAC Emergency Modes of Operation (for
Effectiveness of Entrance Card-Key System(s).
Speech Privacy.
Effectiveness of Electronic Security.
Functionality of Assistance/Alarm Systems.
Effectiveness of Building Automation System Interface.
Functionality of Applied Innovative Technologies.