Feasibility Study Phase
4.2 Submit Project for Funding
Once the project submission has been completed, it is prioritized within the Region
and then included in the Regional Office's Capital Investment and Leasing Program
(CILP) request to GSA in Washington, DC.
Recommended Activities
Submit the Site/Design Prospectus funding proposal. Revise if requested.
Ensure that the Feasibility Study team leader works with the regional
Office of Real Property Asset Management to respond to any requests for
revision or clarification. The team leader coordinates this work with
appropriate Feasibility Study team members and expedites the responses.
Outcome
Completed and submitted Site/Design Prospectus package
Duration
This task typically takes one (1) day.
89