MID RISE FEDERAL COURTHOUSE REFERENCE ESTIMATE
Prepared: 1 August 2003
Date: October 2003
Tenant Improvements
Area: 15,000 USF
Basement Parking
DESCRIPTION
QUANTITY
UNIT
RATE
SUBTOTAL
TOTAL
D50
Electrical
D5020 Metal halide fixtures at 20' on centers, lobby
15,000 GSF
||content||
.15
,250
D5040 Fire alarm A/V and detection devices, security
office telecom raceway, emergency telephone
15,000 GSF
,950
outlets
D5050 Communication and Security Systems included
incl
in D5040 above
25,200
Total D50 Electrical
E
EQUIPMENT & FURNISHINGS
E10
Equipment
E1009 Commercial / Institutional Equipment
Control booth at parking entry/exit complete
1 EA
,100.00
,100
booth and raised island as base
Hydraulic barrier as per "Nasatka Barrier Inc" at
1 EA
,100.00
,100
entrance and exit to garage
GSA to provide parking security equipment as
part of security special requirements
59,200
Total E10 Equipment
817,145
Estimated Final Cost