communication structures and a general description of the systems to be
Commissioning Systems
Selection Matrix
commissioned. This preliminary version of the Plan shall be developed by the
Appendix B of the Building
GSA PM in conjunction with the Customer Agency. The suggested structure of
Commissioning Guide provides
a tool for selecting systems to
commission for a particular facility
must be project specific.
type. Exact systems shall be
determined an a project to project
Introduction
Purpose and general summary of the Plan.
basis.
General Project
Overview of the project, emphasizing key project information an de-
Information
livery method characteristics.
The commissioning scope including which building assemblies,
Commissioning Scope
systems, subsystems and equipment will be commissioned on this
project.
Project specific Commissioning Team members and contact infor-
Team Contacts
mation.
Communication Plan &
Documentation of the communication channels to be used through-
Protocols
out the project.
Detailed description of the project specific tasks to be accom-
Commissioning Process
plished during the Planning, Design, Construction and Tenant Oc-
cupancy Stages with associated roles & responsibilities.
Commissioning
List of commissioning documents required to identify expectations,
Documentation
track conditions and decisions and validate/certify performance.
Specific sequences of events and relative timeframes, dates and
Commissioning Schedule
durations.
The Commissioning Agent will add to this preliminary Plan in the Design
and Construction Phases by assembling and completing the Commissioning
Plan Appendices as detailed below. The completed Appendices will form the
Commissioning Record turned over at the end of the construction stage (see
"Turnover Commissioning Record").
building commissioning
14
process