Section 2: Individual LEED Credit Reviews
Summary of First Cost Impacts
Courthouse (New Construction, 262,000 GSF)
Total Credit Cost ........................................ ,105
Cost Impact ($/GSF)...........................
||content||
.08/GSF
Cost Impact (%)............................................ 0.04%
Minimal Faade Renovation
Total Credit Cost ........................................ ,261
Cost Impact ($/GSF)...........................
||content||
.11/GSF
Cost Impact (%)............................................ 0.08%
Full Faade Renovation
The credit is not pursued.
Additional Considerations
qualify for Credits MR-1.1 - MR-1.3 (Building
Reuse), the project may apply the tonnage of
reused building toward Credit MR-2. The building
materials have, in essence, been diverted from the
landfill. In these cases, the 75 percent waste
reduction criteria may be achieved at limited or no
cost.
Synergistic Credits
Credit MR-2.1 (Construction Waste Management,
50 percent) reviews the cost impacts for achieving
50 percent recycling of construction and
demolition waste.
GSA LEED COST STUDY